NEC4 Alliance contract
Contents[hide] |
[edit] Introduction
The construction industry is continually being challenged to deliver improvements in the outcome of projects and programmes of work. Collaboration and better integration of teams are seen as ways to achieve this.
NEC has been at the forefront of the process, creating a suite of contracts that allow all members of the supply chain to be engaged on similar terms and conditions.
[edit] Moving towards alliancing
Demand for better integration of teams continues – particularly for large, highly complex projects and programmes. In these situations, some clients have adopted a fully integrated delivery model known as an 'alliance'.
An alliance is where the client and key members of the supply chain are engaged under a single multi-party contract with shared objectives, risks and rewards. In the UK and internationally, most notably Australia, alliances have delivered better outcomes for both clients and suppliers, with increased efficiency and fewer disputes.
In 2015, the UK government advisory body Infrastructure UK published 'Improving Infrastructure Delivery: Alliancing Code of Practice'. This said there was a clear business case for using alliancing as a procurement route, with increased efficiency being delivered through behavioural and cultural change.
[edit] New NEC4 Alliance Contract (ALC)
Existing NEC contracts are bi-party arrangements onto which an alliance arrangement can be overlaid, such as by using secondary option X12. In 2016, NEC worked with the UK Infrastructure Client Group to publish Guidance on implementing alliancing using NEC3 contracts.
NEC users have requested the development of a distinct alliancing form in which all participants are engaged under a single multi-party contract. This has led to development of the new NEC4 Alliance Contract (ALC), which will initially be published in consultative form to allow industry feedback.
The basis of the contract is that all parties work together in achieving client objectives, and share in the risks and benefits of doing so.
The new ALC is therefore very different from other contracts in the NEC4 suite. However, it follows where possible the same principles and structure of other NEC4 contracts with familiar provisions, proactive management processes and terminology.
[edit] Benefits to users
The potential benefit of using the new ALC is a much deeper collaboration between all project participants, bound by common interests and reduced grounds for dispute.
The contract drives appropriate behaviours in the alliance members through:
- An emphasis on outcomes.
- Creation of a commercial model which rewards expected behaviours.
- Alignment of goals with client and suppliers.
- Use of integrated systems and processes.
- A best-for-project philosophy.
Commercial performance is measured at an alliance rather than individual party level, with reward criteria based on client's objectives. All alliance members are engaged on an open-book basis with project-specific incentive arrangements agreed at the outset.
This article was originally published here on 26 June 2017 by ICE. It was written by Matthew Garratt and Ian Heaphy, NEC4 Contract Board Members.
--The Institution of Civil Engineers
[edit] Related articles on Designing Buildings Wiki
- Articles by ICE on Designing Buildings Wiki.
- ICE Conditions of Contract.
- NEC contracts and collaborative working.
- NEC4.
- NEC4 Design, Build and Operate Contract.
- NEC4 - legal and insurance aspects.
- NEC contract change management systems.
- NEC4 contract creates a procurement alliance arrangement for all stakeholders.
- Partnering.
- Procurement route.
Featured articles and news
How can digital twins boost profitability within construction?
A brief description of a smart construction dashboard, collecting as-built data, as a s site changes forming an accurate digital twin.
Unlocking surplus public defence land and more to speed up the delivery of housing.
The Planning and Infrastructure bill oulined
With reactions from IHBC and others on its potential impacts.
Farnborough College Unveils its Half-house for Sustainable Construction Training.
Spring Statement 2025 with reactions from industry
Confirming previously announced funding, and welfare changes amid adjusted growth forecast.
Scottish Government responds to Grenfell report
As fund for unsafe cladding assessments is launched.
CLC and BSR process map for HRB approvals
One of the initial outputs of their weekly BSR meetings.
Architects Academy at an insulation manufacturing facility
Programme of technical engagement for aspiring designers.
Building Safety Levy technical consultation response
Details of the planned levy now due in 2026.
Great British Energy install solar on school and NHS sites
200 schools and 200 NHS sites to get solar systems, as first project of the newly formed government initiative.
600 million for 60,000 more skilled construction workers
Announced by Treasury ahead of the Spring Statement.
The restoration of the novelist’s birthplace in Eastwood.
Life Critical Fire Safety External Wall System LCFS EWS
Breaking down what is meant by this now often used term.
PAC report on the Remediation of Dangerous Cladding
Recommendations on workforce, transparency, support, insurance, funding, fraud and mismanagement.
New towns, expanded settlements and housing delivery
Modular inquiry asks if new towns and expanded settlements are an effective means of delivering housing.
Building Engineering Business Survey Q1 2025
Survey shows growth remains flat as skill shortages and volatile pricing persist.